ECE 562 - Spring 2020
Project 4 - Due Feb 25
You may use any power flow software you wish. However, if you don't use
MATPOWER, then make a note on your project report describing the software
that you used (e.g., PTI's PSS/E version xx, attached C code, attached
Excel spreadsheet). Use the Project 3 secure
(no overload) ESCA 64 Bus Model. Note that branches 1,20,1 and
1,20,2 are identical, so you only need to monitor one, not both.
You will study the Available Transfer Capability (ATC) of an interface
by increasing all of the Pgen in Area 1 or Area 3 (your choice) and increasing
both Pload, Qload for all loads in Area 2. The load increase should be uniform
(i.e., all PQ loads increase by the same percentage). Therefore, the
PQ loads in Area 2 will be uniformly scaled by the same "load scaling
factor" to mimic peak loading conditions.
Available Transfer Capability (ATC) based on base case
dispatch
- You need to investigate the impact of a transfer from all of the
generators in your Area. To mimic the peak loading conditions of the
transfer, you
first need to determine the relative contribution of each generator in
your Area. This should be done by determining proportionality factors
based on the initial Pgen output of each generator in your Area.
- The transfer will feed additional load in Area 2. You need to
determine the relative contribution of each load bus in the total
increase of Pload and Qload in Area 2. This should be done by
determining proportionality factors based on the initial Pload demands of
each load bus in Area 2.
- Use the Power Transfer Distribution Factors (PTDF's) and the
proportionality factors from the previous two steps to calculate
the Participation Factors for the branches in your Area (the "From Area")
and the tie-lines between your Area and Area 2 (the "To Area"). You can
ignore the branches within Area 2 as well as those connected to and within
the remaining Area (i.e., you don't have to monitor them).
- Calculate the Available Loading Capacities (ALC's) for the branches
you are monitoring.
- Calculate the individual ATC's for the branches that you are
monitoring.
- Determine the system ATC and the critical element for the normal
case transfer (i.e., all facilities in-service) based on the PTDF's.
- Solve a single power flow with the new PQ load values (any increase
to a PQ load must retain the original PQ load power factor) and the new
Pgen values that correspond to the maximum transfer point (i.e., the
point at which a
branch MVA limit is reached, hence the maximum transfer capability is
reached). Ignore the generators' Pmax values.
- Compare the "monitored" branch MW flows from your PTDF calculations
with the actual MVA branch flows from power flow. When computing the
actual MVA branch flow, use the MVA flow at the "FROM END" of the branch.
Deliverables
- Submit a brief description of your ATC study (e.g., transfer
direction, critical element, etc.).
- Submit the following tables for the "monitored branches" which list
the from bus, to bus, base case MW and MVAR flows, the ParFac's,
the ALC's,
the iATC's, the estimated MW flows at the limit point, the actual MW and
MVAR flows, the actual MVA flows, the "MW relative percentage error" defined
by (MW estimate - actual MW)/MVA rating, and the "MVA relative percentage error"
defined by (|MW estimate| - actual MVA)/MVA rating.
- Top 10 loaded branches based on actual MVA percentage loading
- Top 10 MW percentage loading prediction errors (ranked by magnitude
of prediction error, but shown in table with sign of error)
- Top 10 MVA percentage loading prediction errors
- Any other ranking that illustrates an important point
- Submit formulas for the branch MW flow estimates. Include the
dependence on the PTDF's.
- Analyze the accuracy of your ATC values with respect to the actual
MVA flows. Did the distribution factors underestimate the ATC?
Did they overestimate the ATC?
- Discuss the advantages/disadvantages of using distribution factors
for ATC calculations.
- Propose solutions that would overcome the disadvantages of using
distribution factors for ATC calculations. Be sure to mention any
negative side-effects of your proposed solutions.
- All students must submit the code (MATLAB, C, Excel spreadsheet, etc.)
they used to calculate the ATC values as a section
within the report. Then, the report file must be submitted via
SafeAssignment on Blackboard. Main Campus students also must submit
a hardcopy report at the beginning of class.
Updated 3 Mar 2020